Business Bay, Dubai, United Arab Emirates +971 50 653 1334 +971 55 801 8669 legal@lawyersuae.com
English
Construction Delay & Damages · Dubai, UAE

Construction Delay Compensation Claims in Dubai

A contractor can claim time, and sometimes money, where delay was caused by the employer or a risk the employer bears. The employer can claim where the contractor was responsible. Compensation turns on proof of cause and loss.

What do I need to show?

The delay event, its effect on the programme's critical path, notices given, and the cost incurred. Contemporaneous records are far stronger than retrospective analysis.

What costs are claimable?

Site overheads, idle plant and labour, extended supervision and financing costs, if the contract allows and they are proved. Head office overheads are contentious.

Who should analyse the delay?

A planning expert in substantial cases. We instruct and frame the questions. See extension of time and employer delays.

Documents to have ready

  • Baseline and updated programmes
  • Delay notices
  • Site diaries
  • Cost records
  • Correspondence on causes

Send us the documentsA short message and the key papers are enough for a first assessment.

WhatsApp us

Common questions

Can both parties be responsible for delay?

Yes. Concurrent delay is a recognised issue and the contract may allocate it.

Is time or money more important?

Often time first, because it protects against damages. Money follows if the contract allows.

More on construction delay & damages

This page is general information based on UAE and Dubai legislation as we understand it at the date of drafting. It is not legal advice. Laws are amended, and the right step depends on your documents and facts. Outcomes are never guaranteed.

WhatsApp